MGNREGS

PHYSICAL AND FINANCIAL PROGRESS UPTO JULY 2ND WEEK

Person-days Generated for FY 2019-20 upto July 2nd week
Sl. No. Implementing Agency Total Labour Budget for Total Labour Budget for Total Labour Budget for
Projected Persondays for FY 2019-20 Achieved % of Ach.
1 Jharsuguda 1,32,869 57,971 43.63
2 Kirmira 1,33,803 33,886 25.33
3 Kolabira 1,83,582 60,450 32.93
4 Laikera 2,02,011 56,676 28.06
5 Lakhanpur 3,47,735 1,04,266 29.98
District Total 10,00,000 3,13,249 31.32
Financial Achievement under MGNREGS for FY 2019-20
Sl. No. Implementing Agency Expenditure (in lakh) Upto the Month of July 2nd week Expenditure (in lakh) Upto the Month of July 2nd week Expenditure (in lakh) Upto the Month of July 2nd week
Projected Expenditure Achieved % of Ach.
1 Jharsuguda 441.3 134.71 30.53
2 Kirmira 444.4 131.84 29.67
3 Kolabira 609.73 158.77 26.04
4 Laikera 670.94 132.96 19.82
5 Lakhanpur 1154.93 234.41 20.30
5  Jharsuguda Total 3321.3 792.69 23.87