Physical Progress under Rural Housing Scheme – Jharsuguda
Report as on 10th July 2019
Pradhan Mantri Awaas Yojana
Sl No. |
BLOCK |
SPILLOVER TARGET |
TARGET FOR FY 2019-20 |
TOTAL TARGET |
HOUSE COMPLETED |
% of Achiev. |
1 |
Jharsuguda |
215 |
1453 |
1668 |
69 |
4 |
2 |
Kirmira |
115 |
1704 |
1819 |
51 |
3 |
3 |
kolabira |
58 |
1480 |
1538 |
20 |
1 |
4 |
Laikera |
202 |
1339 |
1541 |
62 |
4 |
5 |
Lakhanpur |
730 |
6024 |
6754 |
262 |
4 |
|
TOTAL |
1320 |
12000 |
13320 |
464 |
3 |
Biju Pucca Ghar Yojana
Sl No. |
BLOCK |
SPILLOVER TARGET |
TARGET FOR FY 2019-20 |
TOTAL TARGET |
HOUSE COMPLETED |
% of Achiev. |
1 |
Jharsuguda |
36 |
0 |
36 |
14 |
39 |
2 |
Kirimira |
23 |
0 |
23 |
8 |
35 |
3 |
kolabira |
9 |
0 |
9 |
6 |
67 |
4 |
Laikera |
16 |
0 |
16 |
6 |
38 |
5 |
Lakhanpur |
112 |
0 |
112 |
44 |
39 |
|
TOTAL |
196 |
0 |
196 |
78 |
40 |